How to build a CNG Filling station
In Italy, depending on the region, a CNG filling station can be realized as a solely installation or in order to differentiate the fuel offer in an already existing station.
The procedure for the realization can be summarized as follow:
1. Planning / Feasibility
- Area location
- eligibility in full obedience of the overall development plan
- other restriction due local current regulations
- possibility of connection to the natural gas grid
- possibility of power supply
- safety regulations
- Feasibility project
- preliminary project of the installation
- costs and profitability analysis of the investment
- environmental impact analysis (use of renewable energies for energy consumption reduction)
- Authorizations inquiry
- declaration of the suitability of the area for the pecific installation from the cognizant Municipality
- fire department preventive advice
- licence for fuel selling (station asset and mode of se - private or open to the public)
- planning permission (from the cognizant Municipality), s well as the environmental impact nalysis and the sanitary authorization
- permit for road access.
2. Final project
- Executive project and technical specifications
- Tender specifications (if necessary)
- Call for funds (if available).
3. R ealization / Work supervision / Final inspection
- Turn-key realization and full-service contract (for rivate fleet it may be included also the supply nd maintenance of the buses as well as the reorganization f the garages)
- Work supervision and safety coordination
- Final inspection and issuing of all permits necessary for the running of a CNG station (fiscal licence, fire prevention certificate, other authorizations).
Italian current regulations for CNG filling station realization
- D.M. 24 maggio 2002 e s.m.i. “Norme di prevenzione ncendi per la progettazione, costruzione ed sercizio degli impianti di distribuzione stradale i gas naturale per autotrazione” - fire prevention egulation for CNG road filling stations
- D.M. 24 novembre 1984 “Norme di sicurezza antincendio per il trasporto, la distribuzione, laccumulo e l’utilizzo del gas naturale con densità non superiore a 0,8 - Parte prima - Sezione terza per le condotte e i pezzi speciali dell’impianto gas” - fire prevention regulation for CNG tubing
- D.Lgs. n. 93 del 25 febbraio 2000 - Attuazione
- Direttiva 97/23/CE - for CNG vessels
- Norma CEI 64-8 (IV ed.) - for electrical system
- Direttiva 94/9/CE del 23 marzo 1994 (Atex) - for electrical system
- Norma CEI EN 60079-10 (classif. 31-30) “Costruzioni elettriche per atmosfere esplosive per la presenza di gas - Parte 10 - Classificazione dei luoghi pericolosi” - for electrical system in case of CNG installations
- Norma CEI 31-35 (classif. 31-35) “Costruzioni elettriche per atmosfere esplosive per la presenza di gas - Guida alla classificazione dei luoghi pericolosi” - for electrical system in case of CNG installations.